The record of building the priest's new living quarters | ||
October 20, 2002 | finished ! | |
July 7, 2002 | The parishioners visit the priest's new living quarters. | |
May 13, 2002 | The facade of the priest's new living quarters | |
April 25, 2002 | The entrance of the priest's new living quarters | |
March 19, 2002 | the inside under construction | |
December 5, 2001 | A roof-laying ceremony | |
November 26, 2001 | A lumberyard | |
November, 2001 | foundation work | |
driving in stakes to solidify ground's footing | ||
October, 2001 | A groundbreaking ceremony (October 25) |
|
breaking down the priest's living quarters | ||
September, 2001 | Soot bamboos | |
June, 2001 | The front approach to the temple | |
the temple gate was moved. | ||
priest's living quarters (before rebuilding) |